Arena Structures called in the
Star Events Group over the Christmas holidays to solve a last minute
problem at the Boatshow at London ExCeL.
A 100m x 50m TFS structure from Arena, which formed part of a larger
temporary extension for the venue for this event specifically, contained
the UK's first ever indoor wind surfing arena and was located on
the uneven grounds of the East car park.
Within the structure, a 70m x 30m pool, holding over 2,300 tons
of water, was surrounded by enormous fans on 2 sides and spectator
seating on the other two sides. As the surrounding seats and fan
supports were already installed, Arena Structures required a level
base over the car park, strong enough to hold up all the water in
the plastic lined pool.
The requirement was first relayed to the Star Events Group on 29th
December, with a requirement for installation to be complete by
the 6th January. This posed a huge logistical challenge as all scaffold,
timber and steel merchants were closed until the 5th January.
The deck area had to be 3 times stronger than a ‘normal’ stage floor,
and The Star Events Group quickly designed a solution that used
over 1,000m of structural steel trussing to form the primary supports
for a total of over 6 kilometres of steel box beams that held the
plywood top.
The whole installation took 15 articulated trucks and was completed
in 5 days by a team of sixteen. This was in spite of the only access
being through a 4m wide gap in one corner of the work area.
Due to the short notice, a lot of the design work was done on site,
with The Star Events Group's design manager Steve Horton on site
for part of the time, and Roger Barrett on the other days. The venue
engaged Sir Robert McAlpine Design to deal with the issues of the
ground bearing pressures whilst the Boatshow engaged Campbell Reith
Hill to check all of The Star Event Group’s design work. The local
authority engaged the PGC - Roessler Partnership to check everything
again. Roger joked that he was “about to get a blackboard to chalk
up the time of the next conducted tour under the structure!”
Other key players were Tez Sheals as on-site project manager and
Bob Fennell as crew chief.
Nigel Beaton, Andrew 'Bomber' Phillips and Tez Sheals took turns
on the hugely tedious nightshifts, watching the structure as the
pool was filled. Due to the large quantities of water involved,
Thames Water would only allow the pool to be filled between 9pm
and 7am, to avoid dropping the mains pressure to the point were
East enders couldn't make a cuppa.
Roger Barrett commented: "This was a challenging project due to
the timescale and logistics of the build coupled with the complexities
of the engineering, but it was a true team effort from all involved
and we were delighted to be a part of that professional team."
Following the final fill, a family of small yellow plastic ducks
were found bobbing about in the middle and Star Event Group’s head
office issued a terse 'no comment' when asked how they got there!
|